Friday, June 13, 2008

Week 06

More rain this week.
The removal of excavated material has been delayed.

Steel cages for the structural piles have been delivered to site.
Piling is now expected to commence in the coming week.




Stephen Sharpe is responsible for LIPMAN's services coordination.

Trade packages in the foreground for tendering sub-contractors to price.